| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACAB-023-ADM-EXT3 | SUMINISTRO Y COLOCACION DE TORELO PROVINCE SOUSTON DE 5 X 30 CMS. (MOLDURA) Y ESQUINERO PROVINCE SOUSTON DE 3 X 5.3 CMS. EN BAÑOS DE LA CAMARA AZUETA, INCLUYE: ACARREO DEL MATERIAL HASTA EL 2DO NIVEL, MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION Y FUNCIONAMIENTO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BOQUILLA | BOQUILLA SIN ARENA WHITE PEARL CAJA 5 KG (RDTO. 13 M2/CAJA) | caja | 0.006000 | $68.70 | $0.41 |
| TORRELLO PROVINCE | TORELO PROVINCE SOUSTON DE 5 X 30 CMS. (MOLDURA) | ml | 1.050000 | $269.83 | $283.32 |
| ESQUINERO TORELLO | ESQUINERO PROVINCE SOUSTON DE 3 X 5.3 CMS. | pza | 1.000000 | $89.00 | $89.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | pieza | 0.013200 | $29.69 | $0.39 |
| ADH-ANT-01 | ADHESIVO ANTIDESLIZAMIENTO BLANCO | kg | 0.258000 | $4.30 | $1.11 |
| Suma de Material | $374.24 | ||||
| Mano de Obra | |||||
| CUADRILLA -21 | ( 1 COLOCADOR + 1 AYUDANTE) | jor | 0.100000 | $959.29 | $95.93 |
| 02-0010 | CUADRILLA No 1 ( 1 PEON ) | jor | 0.026316 | $396.90 | $10.44 |
| Suma de Mano de Obra | $106.37 | ||||
| Equipo | |||||
| ESMERILADORA | ESMERILADORA | hora | 0.030000 | $5.59 | $0.17 |
| Suma de Equipo | $0.17 | ||||
| Auxiliar | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.001440 | $69.04 | $0.10 |
| 03-7022 | TORRE DE TRABAJO DE 0.00 A 4.00 MTS. DE ALTURA CON RUEDAS | R/D | 0.100000 | $26.82 | $2.68 |
| Suma de Auxiliar | $2.78 | ||||
| Costo Directo | $483.56 |