| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACAB-016-ADM-EXT3 | SUMINISTRO Y COLOCACION DE PISO DE MARMOL CARRARA CON MEDIDAS DE LA PIEZA DE 0.15 X 0.30 MTS. EN BAÑOS Y SALA PRINCIPAL DE LA CAMARA AZUETA, INCLUYE: ACARRERO DEL MATERIAL HASTA EL 2DO NIVEL, MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION Y FUNCIONAMIENTO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BOQUILLA | BOQUILLA SIN ARENA WHITE PEARL CAJA 5 KG (RDTO. 13 M2/CAJA) | caja | 0.076923 | $68.70 | $5.28 |
| PARQUET MARMOL | PARQUET DE MARMOL CON MEDIDAS DE 15 X 30 CMS. | M2 | 1.050000 | $380.00 | $399.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | pieza | 0.013200 | $29.69 | $0.39 |
| ADH-ANT-01 | ADHESIVO ANTIDESLIZAMIENTO BLANCO | kg | 4.750000 | $4.30 | $20.43 |
| BOQ-EPOX-01 | BOQUILLA EPOXICA 100% SOL. EPOXY GRT. WHITE | kg | 0.250000 | $50.00 | $12.50 |
| Suma de Material | $437.60 | ||||
| Mano de Obra | |||||
| CUADRILLA -21 | ( 1 COLOCADOR + 1 AYUDANTE) | jor | 0.166667 | $959.29 | $159.88 |
| 02-0010 | CUADRILLA No 1 ( 1 PEON ) | jor | 0.020000 | $396.90 | $7.94 |
| Suma de Mano de Obra | $167.82 | ||||
| Equipo | |||||
| ESMERILADORA | ESMERILADORA | hora | 0.100000 | $5.59 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Auxiliar | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.008000 | $69.04 | $0.55 |
| Suma de Auxiliar | $0.55 | ||||
| Costo Directo | $606.53 |