| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | | | | |
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.082400 | $1,201.82 | $99.03 |
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.082400 | $1,201.82 | $99.03 |
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.082400 | $1,201.82 | $99.03 |
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | m3 | 0.082400 | $1,201.82 | $99.03 |
| Suma de Auxiliar | | | | $396.12 |
| Concepto | | | | |
| 020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. INCLUYE: SUMINISTRO, HABILITADO, ARMADO, COLOCACION, ACARREOS INTERNOS, COSTO POR MANO DE OBRA, MATERIALES DE CONSUMO, EQUIPO Y HERRAMIENTA. | m2 | 1.000000 | $126.06 | $126.06 |
| 020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. INCLUYE: SUMINISTRO, HABILITADO, ARMADO, COLOCACION, ACARREOS INTERNOS, COSTO POR MANO DE OBRA, MATERIALES DE CONSUMO, EQUIPO Y HERRAMIENTA. | m2 | 1.000000 | $126.06 | $126.06 |
| 020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. INCLUYE: SUMINISTRO, HABILITADO, ARMADO, COLOCACION, ACARREOS INTERNOS, COSTO POR MANO DE OBRA, MATERIALES DE CONSUMO, EQUIPO Y HERRAMIENTA. | m2 | 1.000000 | $126.06 | $126.06 |
| 020227 | CIMBRA COMUN EN LOSA CON TARIMAS DE 50 X 100 CM. INCLUYE: SUMINISTRO, HABILITADO, ARMADO, COLOCACION, ACARREOS INTERNOS, COSTO POR MANO DE OBRA, MATERIALES DE CONSUMO, EQUIPO Y HERRAMIENTA. | m2 | 1.000000 | $126.06 | $126.06 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.006016 | $21,360.86 | $128.51 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.006016 | $21,360.86 | $128.51 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.006016 | $21,360.86 | $128.51 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.006016 | $21,360.86 | $128.51 |
| Suma de Concepto | | | | $1,018.27 |
| Costo Directo | | | | $1,414.39 |