| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Auxiliar | | | | |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.111100 | $21.92 | $2.44 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.111100 | $21.92 | $2.44 |
| CIM022 | CIMBRA EN ALBA脩ILERIA PARA CASTILLO, CADENA, REPIZON O CEJA A BASE DE MADERA DE PINO DE 3a. | m2 | 0.620000 | $131.31 | $81.41 |
| CIM022 | CIMBRA EN ALBA脩ILERIA PARA CASTILLO, CADENA, REPIZON O CEJA A BASE DE MADERA DE PINO DE 3a. | m2 | 0.620000 | $131.31 | $81.41 |
| Suma de Auxiliar | | | | $167.70 |
| Concepto | | | | |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.003528 | $21,360.86 | $75.36 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.003528 | $21,360.86 | $75.36 |
| 020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.001288 | $23,246.04 | $29.94 |
| 020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.001288 | $23,246.04 | $29.94 |
| 020473 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN COLUMNAS Y MUROS. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.065100 | $1,695.11 | $110.35 |
| 020473 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN COLUMNAS Y MUROS. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.065100 | $1,695.11 | $110.35 |
| Suma de Concepto | | | | $431.31 |
| Costo Directo | | | | $599.00 |