| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 041808 | EMBOQUILLADO EN APLANADO PERFILADO UNA ARISTA CON MORTERO CEMENTO-ARENA 1:4 PULIDO CON LLANA METALICA DE 15 CM DE SECCION Y ESPESOR PROMEDIO = 1.5 CM HASTA 3.00 mts. DE ALTURA MAXIMA; INCLUYE: MATERIALES DE CONSUMO, TORRE DE TRABAJO, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.083333 | $889.79 | $74.15 |
| Suma de Mano de Obra | $444.89 | ||||
| Auxiliar | |||||
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | m3 | 0.002575 | $997.17 | $2.57 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.003000 | $69.04 | $0.21 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.066667 | $21.92 | $1.46 |
| Suma de Auxiliar | $25.42 | ||||
| Costo Directo | $470.31 |