| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | | | | |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.111100 | $21.92 | $2.44 |
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.111100 | $21.92 | $2.44 |
| CIM022 | CIMBRA EN ALBAÑILERIA PARA CASTILLO, CADENA, REPIZON O CEJA A BASE DE MADERA DE PINO DE 3a. | m2 | 0.400000 | $131.31 | $52.52 |
| CIM022 | CIMBRA EN ALBAÑILERIA PARA CASTILLO, CADENA, REPIZON O CEJA A BASE DE MADERA DE PINO DE 3a. | m2 | 0.400000 | $131.31 | $52.52 |
| Suma de Auxiliar | | | | $109.92 |
| Concepto | | | | |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.002350 | $21,360.86 | $50.20 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.002350 | $21,360.86 | $50.20 |
| 020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.000862 | $23,246.04 | $20.04 |
| 020317 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 2 DIAMETRO 1/4" INCLUYE:SUMINISTRO, ACARREOS INTERNOS, HABILITADO,ARMADO Y COLOCACION, ALAMBRE RECOCIDO, COSTO POR MANO DE OBRA, SEPARADOR DE CONCRETO PARA CALZAR ACERO, EQUIPO Y HERRAMIENTA. | ton | 0.000862 | $23,246.04 | $20.04 |
| 020473 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN COLUMNAS Y MUROS. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.030000 | $1,695.11 | $50.85 |
| 020473 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN COLUMNAS Y MUROS. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.030000 | $1,695.11 | $50.85 |
| Suma de Concepto | | | | $242.18 |
| Costo Directo | | | | $352.10 |