| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MR-PLA-001-AUL-EXT2 | SUMINISTRO Y COLOCACION DE PLAFON DE DUROCK HASTA UNA ALTURA DE 3.50 MTS. EN LOS PASILLOS DEL EDIFICIO DE AULAS, INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA COLOCACION Y FUNCIONAMIENTO | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABCEM-DRK-001 | TABLACEMENTO MCA. DUROCK DE 12.7 CM. DE ESPESOR | m2 | 1.100000 | $94.73 | $104.20 |
| ALAMBRE GALVANIZADO | ALAMBRE GALVANIZADO | kg | 0.100000 | $27.68 | $2.77 |
| CANALETA DE CARGA | CANALETA DE CARGA USG CAL. 22 | ml | 1.300000 | $8.47 | $11.01 |
| CANAL LISTON | CANAL LISTON USG CAL. 26 | ml | 2.000000 | $8.66 | $17.32 |
| ANGULO D AMARRE | ANGULO DE AMARRE | pieza | 0.250000 | $10.60 | $2.65 |
| TORNILLO S-1 | TORNILLOS S-1 | pieza | 12.000000 | $0.05 | $0.60 |
| ANCLAS | ANCLAS HILTI | pieza | 1.500000 | $5.50 | $8.25 |
| FULMINANTE VERDE | FULMINANTE VERDE | pieza | 1.500000 | $1.38 | $2.07 |
| CINT-REF-001 | CINTA DE REFUERZO MCA. DUROCK DE 10 CM. | ml | 4.510000 | $1.44 | $6.49 |
| ADES-DRK-001 | ADHESIVO DUROCK BASECOAT CEMENTO FLEXIBLE | kg | 3.737500 | $10.14 | $37.90 |
| Suma de Material | $193.26 | ||||
| Mano de Obra | |||||
| CUADRILLA -25 | (1 OFICIAL DE TABLAROCA + 1 AYUDANTE) | jor | 0.166667 | $963.43 | $160.57 |
| Suma de Mano de Obra | $160.57 | ||||
| Auxiliar | |||||
| 03-7013 | TORRE DE TRABAJO DE 0.00 A 2.00 MTS DE ALTURA CON RUEDAS | R/D | 0.100000 | $21.92 | $2.19 |
| Suma de Auxiliar | $2.19 | ||||
| Costo Directo | $356.03 |