| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SALSAN-001 | SALIDA SANITARIA, INCLUYE:TUBO PVC SANITARIO 152 mm, TUBO PVC SANITARIO DE 151 mm, TUBO DE PVC SANITARIA DE 52 mm, CODO DE PVC DE 152 mm x 90º, CODO DE PVC DE 101 mm x90º, CODO DE PVC DE 52 mm x 90º, TEE PVC DE 152 mm, TEE PVC DE 101 mm, TEE DE PVC DE 52 mm, REDUCCION DE PVC DE 152mm A 101 mm, REDUCCION DE PVC DE 101 mm A 52 mm, COLADERA DE 152 mm, COLADERA DE 52 mm, YEE DE PVC SANITARIA 152 mm, YEE DE PVC SANITARIA DE 52 mm, PEGAMENTO PARA PVC , MANO DE OBRA, HERRAMIENTA MENOR , ACARREO DE LOS MISMO , DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | SALIDA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IE-73 | Tubo pvc san de 100 mm | m | 6.580000 | $21.50 | $141.47 |
| IE-74 | Tubo pvc san de 50 mm | m | 3.800000 | $18.10 | $68.78 |
| IE-75 | Codo pvc san de 50 x 90° | pza | 2.000000 | $1.63 | $3.26 |
| IE-76 | Cople pvc san de 50 mm | pza | 1.000000 | $1.13 | $1.13 |
| IE-77 | Cople pvc san de 100 mm | pza | 1.000000 | $3.39 | $3.39 |
| IE-78 | Cespol de bote san una salida de 50 mm | pza | 1.000000 | $16.97 | $16.97 |
| IE-79 | Yee pvc san de 100 mm | pza | 1.000000 | $13.43 | $13.43 |
| IE-80 | Yee pvc san de 50 mm | pza | 1.000000 | $3.46 | $3.46 |
| IE-81 | Cople pvc san salida lateral de 50 mm | pza | 1.000000 | $9.54 | $9.54 |
| IE-82 | Codo pvc san de 50 x 45° | pza | 1.000000 | $1.34 | $1.34 |
| IE-83 | Codo pvc san de 100 x 45° | pza | 1.000000 | $5.30 | $5.30 |
| IE-84 | Yee pvc san de 100 x 50 mm | pza | 1.000000 | $7.78 | $7.78 |
| IE-85 | Codo pvc san de 100 x 90° | pza | 1.000000 | $7.07 | $7.07 |
| IE-86 | Tee pvc san de 50 mm | pza | 1.000000 | $2.26 | $2.26 |
| IE-87 | Tee reduccion san 1913 y 19 | pza | 1.000000 | $24.74 | $24.74 |
| IE-88 | Tee pvc san de 38 mm | pza | 1.000000 | $144.21 | $144.21 |
| IE-89 | Tee pvc san de 32 mm | pza | 1.000000 | $106.74 | $106.74 |
| IE-90 | Tee pvc san de 25 mm | pza | 1.000000 | $50.90 | $50.90 |
| IE-91 | Reduccion bushing san de 25 x 19 mm | pza | 1.000000 | $9.54 | $9.54 |
| IE-92 | Reduccion bushing san de 32 x 25 mm | pza | 1.000000 | $16.61 | $16.61 |
| IE-93 | Reduccion bushing san de 38 x 32 mm | pza | 1.000000 | $16.61 | $16.61 |
| IE-94 | Pasta de 250 grs | pza | 1.525000 | $29.34 | $44.74 |
| IE-95 | Segueta fina | pza | 2.000000 | $7.78 | $15.56 |
| IE-96 | Lija | m | 1.000000 | $7.33 | $7.33 |
| IE-97 | 711 T 32 mm, san | pza | 1.000000 | $6.74 | $6.74 |
| Suma de Material | $728.90 | ||||
| Mano de Obra | |||||
| A100110-2020 | Cuadrilla de plomeros. Incluye : plomero, ayudante, cabo y herramienta. | Jor | 1.345340 | $1,036.88 | $1,394.96 |
| Suma de Mano de Obra | $1,394.96 | ||||
| Costo Directo | $2,123.86 |