| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C-1 | MURO DE BLOCK DE CONCRETO HUECO DE 20X20X40 CM EN 20 CM DE ESPESOR ASENTADO CON MORTERO CEMENTO ARENA 1:5, ACABADO COMUN, ALTURA HASTA 2.00 M. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0534-00 | BLOCK DE CONCRETO PESADO DE 20 X 20 X 40 CM HUECO | MILL | 0.012900 | $4,800.00 | $61.92 |
| 0121-00 | REFUERZO HORIZONTAL PARA MURO DE BLOCK | ML | 1.000000 | $14.50 | $14.50 |
| 0084-01 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.001110 | $9,130.43 | $10.13 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.205000 | $14.50 | $2.97 |
| SEGURIDAD IND. | SEGURIDAD INDUSTRIAL PARA PERSONAL | LOTE | 1.000000 | $2.00 | $2.00 |
| Suma de Material | $91.53 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.072410 | $559.85 | $40.54 |
| Suma de Mano de Obra | $40.54 | ||||
| Auxiliar | |||||
| 03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 0.009000 | $768.01 | $6.91 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.040000 | $20.08 | $0.80 |
| Suma de Auxiliar | $7.72 | ||||
| Concepto | |||||
| 020406 | CONCRETO HECHO EN OBRA RESISTENCIA RAPIDA VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVNIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION | M3 | 0.022500 | $1,055.99 | $23.76 |
| Suma de Concepto | $23.76 | ||||
| Costo Directo | $163.54 |