| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-3 | ZAPATA CENTRAL TIPO ZC2 DE 0.80 X 0.15 M. DE PERALTE ARMADA CON VARILLAS DEL No. 3 @ 20CM AMBOS SENTIDOS SEGUN CROQUIS, INCLUYE: CONCRETO HECHO EN OBRA DE F'C=250KG/CM2. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SEGURIDAD IND. | SEGURIDAD INDUSTRIAL PARA PERSONAL | LOTE | 1.000000 | $2.00 | $2.00 |
| Suma de Material | $2.00 | ||||
| Concepto | |||||
| 020201 | CIMBRA Y DESCIMBRA COMUN DE CONTACTO | M2 | 0.300000 | $183.52 | $55.06 |
| 020405 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" | M3 | 0.119000 | $1,534.54 | $182.61 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.006410 | $12,451.29 | $79.81 |
| Suma de Concepto | $317.48 | ||||
| Costo Directo | $319.48 |