| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-1 | ZAPATA DE CIMENTACION CORRIDA ZC1 INCLUYE CIMBRA Y DESCIMBRA ANCHO DE 0.80 X 0.18 M. DE PERALTE ARMADA CON VARILLAS DEL No. 3 @20CM AMBOS LECHOS Y SENTIDOS SEGUN CROQUIS, INCLUYE: CONCRETO HECHO EN OBRA F'C=250 KG/CM2-3/4" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SEGURIDAD IND. | SEGURIDAD INDUSTRIAL PARA PERSONAL | LOTE | 1.000000 | $2.00 | $2.00 |
| Suma de Material | $2.00 | ||||
| Concepto | |||||
| 020201 | CIMBRA Y DESCIMBRA COMUN DE CONTACTO | M2 | 0.150000 | $183.52 | $27.53 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.009000 | $12,451.29 | $112.06 |
| 020407 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=250 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION | M3 | 0.140000 | $1,268.62 | $177.61 |
| Suma de Concepto | $317.20 | ||||
| Costo Directo | $319.20 |