| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7.373 | INSTALACIÓN DE CARTUCHO DE 15, 20 Y 25 AMP. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.100000 | $22.50 | $2.25 |
| Suma de Material | $2.25 | ||||
| Mano de Obra | |||||
| CUAD-08 | CUADRILLA DE ELECTRICISTA | JOR | 0.033333 | $5,898.48 | $196.61 |
| Suma de Mano de Obra | $196.61 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.025000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| ESCALERA | ESCALERA DE TIJERA MARCA CUPRUM | HORA | 0.100000 | $0.39 | $0.04 |
| AME-01 | ANDAMIO METALICO TOTAL ATLAS SYSTEM CON ACCESORIOS | HORA | 0.100000 | $73.53 | $7.35 |
| MOLDE | MOLDE PARA APLICACION DE CARGAS | HORA | 0.200000 | $1.46 | $0.29 |
| Suma de Equipo | $7.68 | ||||
| Costo Directo | $206.55 |