| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| R1 | Reparacion de linea de conducci贸n | pza |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REP1 | Poliducto 1 1/2" | m | 1.000000 | $18.00 | $18.00 |
| REP40 | Lubricante | kg | 0.125000 | $50.00 | $6.25 |
| REP2 | Poliducto 2" | m | 1.000000 | $25.00 | $25.00 |
| REP37 | Cable uso rudo | m | 8.000000 | $30.00 | $240.00 |
| REP3 | Cinta de aislar | pza | 1.000000 | $15.00 | $15.00 |
| REP5 | Pegamento para pvc Siler 480 ml | lata | 1.000000 | $120.00 | $120.00 |
| REP18 | TUBO RD-26 100 | tubo | 1.000000 | $700.00 | $700.00 |
| REP19 | COPLE REP 100 C/ ANILLO | pza | 2.000000 | $180.00 | $360.00 |
| REP20 | COPLE REP 100 | pza | 0.000000 | $100.00 | $0.00 |
| REP21 | LIMPIADOR | lata | 1.000000 | $20.00 | $20.00 |
| REP22 | CEMENTO 480 ML | lata | 0.000000 | $70.00 | $0.00 |
| Suma de Material | $1,504.25 | ||||
| Mano de Obra | |||||
| SUPERVISOR | Ing. Supervisor especialista en sistemas de riego | jor | 3.000000 | $600.00 | $1,800.00 |
| Suma de Mano de Obra | $1,800.00 | ||||
| Herramienta | |||||
| 3HER | herramienta menor | (%)mo | 0.060000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Contrato | |||||
| MOR1 | Reparaci贸n tuber铆a 4" Reparaci贸n tuber铆a 4" | reparaci贸n | 1.000000 | $700.00 | $700.00 |
| Suma de Contrato | $700.00 | ||||
| Costo Directo | $4,004.25 |