| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 53 | PRIMARIO RP-6 COLOR ROJO OXIDO CON CATALIZADOR | LT |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| C-001-CDS | TRAPO DE PRIMERA | KG | 0.100000 | $20.51 | $2.05 |
| PINTA | PINTURA PRIMARIO ESP PEMEX | LTS | 3.000000 | $120.00 | $360.00 |
| THINER | THINER AMERICANO | LTS | 1.000000 | $7.00 | $7.00 |
| RES | RESANADOR INDUSTRIAL | KGS | 0.010000 | $800.00 | $8.00 |
| Suma de Material | $377.05 | ||||
| Mano de Obra | |||||
| CM09 | CUADRILLA DE PINTOR | JOR | 0.200000 | $819.78 | $163.96 |
| Suma de Mano de Obra | $163.96 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQUIPO8 | EQUIPO DE PINTURA COMPLETO PORTATIL MARCA ATLAS COPCO MOD TR564FE | HORA | 4.000000 | $12.28 | $49.12 |
| Suma de Equipo | $49.12 | ||||
| Costo Directo | $590.13 |