| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 17 | SUM E INSTALACION DE PLACA DEL SISTEMA DE TIERRA SOLDADA AL TR | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOL005 | DISCO ABRASIVO MARCA AUSTROMEX No. 741 | PZA | 0.100000 | $120.00 | $12.00 |
| PLACA | SUM E INSTALACION DE PLACA DEL SISTEMA DE TIERRA SOLDADA AL TR | PZA | 1.000000 | $800.00 | $800.00 |
| SOL006 | CEPILLO TIPO CARDA DE ALAMBRE TRENZADA, MARCA AUSTROMEX. | PZA | 0.040000 | $94.20 | $3.77 |
| SOL001 | GAS ACETILENO, MARCA INFRA | KG | 0.020000 | $304.00 | $6.08 |
| SOL002 | GAS OXIGENO, MARCA INFRA | M3 | 0.010000 | $168.32 | $1.68 |
| SOL003 | SOLDADURA ELECTRODO REVESTIDO TIPO E-7018/6010, MARCA INFRA. | KG | 0.100000 | $39.64 | $3.96 |
| Suma de Material | $827.50 | ||||
| Mano de Obra | |||||
| CUA02 | CUADRILLA DE PAILERO + AYUDANTE | JOR | 0.010000 | $1,209.12 | $12.09 |
| CUA23 | CUADRILLA 2 MANIOBRISTAS | JOR | 0.003333 | $995.95 | $3.32 |
| CUA01 | CUADRILLA DE SOLDADOR + AYUDANTE | JOR | 0.006667 | $1,291.11 | $8.61 |
| Suma de Mano de Obra | $24.02 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AME-09 | PULIDOR ELECTRICO DE 1 H.P. MILWAUKEE, CON 50 MTS. DE CABLE, CAPACIDAD DE DISCO DE 4 1/2", 10.000 R.P.M. MOD. B11HR51 | HORA | 0.100000 | $2.75 | $0.28 |
| AME-03 | TALADRO ELECTRICO INDUSTRIAL CON BROCAS VARIAS MEDIDAS MARCA BLACK & DECKER MOD. B11XD90 | HORA | 0.100000 | $4.14 | $0.41 |
| AME-05 | HORNO ELECTRICO PARA SOLDADURA MARCA LINCOLN DE 5 KG DE CAPACIDAD | HORA | 0.100000 | $1.80 | $0.18 |
| AME-04 | EQUIPO COMPLETO DE OXIACETILENO PARA CALENTAMIENTO Y CORTE MCA. VICTOR INCLUYE REGULADOR PARA OXIGENO, PARA ACETILENO, MANERAL, BOQUILLAS PARA CORTE DEL 1 AL 5, DESTAPABOQUILLAS Y 25 MTS. DE MANGUERA DUPLEX CON CONEXIONES MOD. MP80DLX | HORA | 0.100000 | $6.40 | $0.64 |
| Suma de Equipo | $1.51 | ||||
| Auxiliar | |||||
| RA-26 | APLICACION DE PINTURA EPOXICO CATALIZADO DE ALTOS SOLIDOS ACABADO RA-26 | M2 | 0.100000 | $111.47 | $11.15 |
| RA-28 | APLICACION DE PINTURA ACABADO RA-28 | M2 | 0.100000 | $108.20 | $10.82 |
| AUX-93 | LIMPIEZA CON CHORRO DE ARENA A METAL BLANCO (SANDBLAST) | M2 | 0.100000 | $156.77 | $15.68 |
| AUX-RP-4B | APLICACIÓN DE PRIMARIO, RP-4B MODIFICADO (UNA CAPA DE 75 MICRAS) | M2 | 0.100000 | $114.04 | $11.40 |
| Suma de Auxiliar | $49.05 | ||||
| Costo Directo | $902.07 |