| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 36 | REALIZAR REBARNIZADO Y HORNEADO DE DEVANADOS Y NUCLEO PARA CORRECCION DE BAJO NIVEL DE AISLAMIENTO HASTA DE 700 KVA, INCLUYE: DESCONEXION INTERNA DE BOQUILLAS Y DE PALANCA DE TAPS, IDENTIFICACION DE TERMINALES, SUSTRACCION DE NUCLEO CON CAMION HIAB, COOCACION EN BASE PARA LAVADO CON SOLVENTE DIELECTRICO SS-25, SOPLETEADO CON AIRE COMPRIMIDO Y NITROGENO POSTERIORMENTE, APLICACION DE BARNIZ DIELECTRICO MEDIANTE ASPERSION, HORNEADO DEL NUCLEO (HORNO ELECTRICO), MONTAJE NUEVAMENTE EN EL INTERIOR DEL TANQUE CONTENEDOR, FIJACION A SU BASE, CONEXIONES DE BOQUILLAS Y TERMINALES, CONEXION CON PALANCA DE TAPS. | SERVICIO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOL1 | SOLVENTE DIELECTRICO SS-25 | LTS | 10.000000 | $140.00 | $1,400.00 |
| NITRO | NITROGENO GAS | M2 | 6.000000 | $320.00 | $1,920.00 |
| AIRE | AIRE COMPRIMIDO PARA LIMPIEZA | M2 | 1.000000 | $80.00 | $80.00 |
| BARNIS | BARNIZ DIELECTRICO | LTS | 12.000000 | $85.00 | $1,020.00 |
| C005SGP | BROCHA DE 2" DE ANCHO, MARCA PERFECT | PIEZA | 2.000000 | $24.50 | $49.00 |
| CINT | CINTURONES DE PLASTICO | PIEZA | 200.000000 | $7.00 | $1,400.00 |
| TO | TORNILLOS DE DIFERENTES MEDIDAS | JGO | 8.000000 | $750.00 | $6,000.00 |
| C-001-CDS | TRAPO DE PRIMERA | KG | 10.000000 | $20.51 | $205.10 |
| Suma de Material | $12,074.10 | ||||
| Mano de Obra | |||||
| CUAD-08 | CUADRILLA DE ELECTRICISTA | JOR | 4.000000 | $6,126.23 | $24,504.92 |
| CUA23 | CUADRILLA 2 MANIOBRISTAS | JOR | 2.000000 | $995.95 | $1,991.90 |
| CM09 | CUADRILLA DE PINTOR | JOR | 1.000000 | $819.78 | $819.78 |
| Suma de Mano de Obra | $27,316.60 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| BOM | BOMBA ESCARCHER | HORA | 12.000000 | $56.28 | $675.36 |
| AME-37 | CAMION CAPACIDAD DE 3.5 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 8.000000 | $194.46 | $1,555.68 |
| HOERNO | HORNO ALTA PEMPERATURA | HORA | 12.000000 | $286.13 | $3,433.56 |
| EQ | EQUIPO DE ASPERSION EMBARNIZADO | HORA | 7.000000 | $45.00 | $315.00 |
| AME-23 | DIFERENCIAL DE CADENA DE 10 TON. DE CAPACIDAD, MARCA COLUMBUS McKINNON DE MEXICO, MODELO CM-622, CON ESLINGAS DE 12 TONELADAS DE CAPACIDAD, MARCA VIKING. | HORA | 5.000000 | $5.03 | $25.15 |
| Suma de Equipo | $6,004.75 | ||||
| Costo Directo | $45,395.45 |