| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 13 | SUM E INSTALACION DE REDUCCION BUSHING ROSCADA DE 11/4" X1/4" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| C-001-CDS | TRAPO DE PRIMERA | KG | 5.000000 | $20.51 | $102.55 |
| MAT 4.1751 | CINTA TEFLON DE 3/8" ANCHO | PZA | 0.200000 | $9.00 | $1.80 |
| 1086M5P | REDUCCION BUSHING ROSCADA DE 11/4" X1 | PIEZA | 1.000000 | $474.31 | $474.31 |
| Suma de Material | $578.66 | ||||
| Mano de Obra | |||||
| CM04 | CUADRILLA DE MANIOBRISTAS | JOR | 0.200000 | $1,025.07 | $205.01 |
| Suma de Mano de Obra | $205.01 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $783.67 |