| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| REF.02.8 | FIRME DE CONCRETO ARMADO DE 23 CM DE ESPESOR, CONSIDERANDO HABILITADO Y ARMADO DEL FIRME CON MALLA ELECTROSOLDADA 6X6 6-6, SILLETAS, CIMBRA, PASAJUNTAS, CORTES, SELLADO DE JUNTAS Y TODO LO NECESARIO PARA LA CORRECTA EJECUCIÒN. | M2 * |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| A GUA | AGUA | m3 | 0.050000 | $45.00 | $2.25 |
| ANGULO 2"X1/4" | ANGULO DE 2" x 1/4" | kg | 0.220000 | $8.00 | $1.76 |
| MALLA 6-6 4/4 | MALLA ELECTROSOLDADA 6/6 6/6 | m2 | 1.050000 | $22.71 | $23.85 |
| PASA JUNTAS | PASAJUNTAS DE ACERO DE REDONDO LISO DEL No. 5 @ 30 CMS. Y 60 CMS. DE LONGITUD. | kg | 1.200000 | $8.55 | $10.26 |
| CELOTEX | JUNTA CONSTRUCTIVA A BASE DE CELOTEX | m2 | 0.100000 | $66.50 | $6.65 |
| SELLO ELASTICO | SELLO ELASTICO SONOMERIC DE SONNEBORN | litro | 0.100000 | $42.75 | $4.28 |
| CONCRETO DE 250 | CONCRETO PREMEZCLADO CPP - R30-RS DE 250 KG/CM2, REVENIMIENTO 1O | m3 | 0.241500 | $920.00 | $222.18 |
| PRUEBAS LABORATORIO | PRUEBAS DE LABORATORIO | m3 | 1.000000 | $5.00 | $5.00 |
| MEMBRANA | MEMBRANA DE CURADO SIKA ANTISOL ROJO | litro | 0.125000 | $24.42 | $3.05 |
| Suma de Material | $279.27 | ||||
| Mano de Obra | |||||
| CUADRILLA OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | jor | 0.040000 | $575.26 | $23.01 |
| Suma de Mano de Obra | $23.01 | ||||
| Equipo | |||||
| API-VIBRADOR CON * | VIBRADOR A GASOLINA PARA CONCRETO MARCA CIPSA, CON MOTOR HONDA DE 5.5 H.P. | hora | 0.800000 | $6.42 | $5.14 |
| Suma de Equipo | $5.14 | ||||
| Costo Directo | $307.42 |