| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBD-15X25-4#3-1/4 | DALA DE CERRAMIENTO SECCION 0.15 X 0.25 MT., CONCRETO F'C=150 Kg/cm2, AGREGADO MAXIMO 3/4", CIMBRA 2 CARAS, REFORZADA CON 4 VARILLAS DE 3/8", ESTRIBOS DE 1/4" A/C 20 CM., SEGUN MARCA PROYECTO, INCLUYE: MATERIAL, MANO DE OBRA, DEPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-MAD-01 | Madera de pino de tercera en duela | pt | 1.368000 | $7.14 | $9.77 |
| OC-ACER-REF6 | Varilla corrugada acero de refuerzo del # 3 (3/8") fy = 4200 kg/cm2 | ton | 0.002340 | $10,800.00 | $25.27 |
| OC-ACER-REF4 | Alambrón de 1/4" de diámetro | kg | 1.117600 | $13.79 | $15.41 |
| OC-ACER-REF5 | Alambre recocido no. 16 | kg | 0.250000 | $12.31 | $3.08 |
| OC-ACER-CLA2 | Clavo de 2 1/2" a 4" | kg | 0.135000 | $20.70 | $2.79 |
| OC-COMB-01 | Diesel | lt | 0.300000 | $9.02 | $2.71 |
| Suma de Material | $59.03 | ||||
| Mano de Obra | |||||
| OC-CUA11 | Cuadrilla (1 albañil + 1 ayudante) | jor | 0.117650 | $941.43 | $110.76 |
| Suma de Mano de Obra | $110.76 | ||||
| Equipo | |||||
| OC-EQUI32 | Vibrador de gasolina marca Felsa modelo vibromax cap. 12000 VPM, con manguera de 4.00 mts, y cabezal de por 38 mm ( 1 1/2"), con motor de gasolina de 4 H. P. | Hora | 0.020000 | $56.55 | $1.13 |
| Suma de Equipo | $1.13 | ||||
| Auxiliar | |||||
| OC-AUX8 | Elaboración de concreto f'c= 150 kg/cm2, agregado de 3/4", incluye cemento, arena, grava y agua, en revenimiento 8 a 10 cm | m3 | 0.039380 | $1,204.61 | $47.44 |
| OC-AUX13 | Andamio tubular de 4 m, con ruedas, plataforma y barras, con tablones. | r/d | 0.117650 | $87.27 | $10.27 |
| Suma de Auxiliar | $57.70 | ||||
| Costo Directo | $228.62 |