| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 104 | TRABE DE CIMENTACION DE 0.20X0.40 M. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-02 | ALAMBRE REC. | KG | 0.240000 | $8.82 | $2.12 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $8.27 | $9.92 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $72.00 | $14.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $10.00 | $1.00 |
| ACERO-06 | ACERO DE NO. 3 | KG | 7.380000 | $6.52 | $48.12 |
| Suma de Material | $75.56 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.050000 | $1,109.21 | $55.46 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.090000 | $481.43 | $43.33 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.070000 | $481.43 | $33.70 |
| Suma de Mano de Obra | $132.49 | ||||
| Auxiliar | |||||
| CONCRETO H.O-01 | CONCRETO HECHO EN OBRA F'C = 250 KG/CM2. AGREGADO GRUESO MAXIMO DE 3/4" REVENIMIENTO 10 CM RESISTENCIA NORMAL, GRADO TIPO 'A' ESTRUCTURAL PARA FORMACION DE ZAPATAS INCLUYE: SUMINISTRO DE LOS MATERIALES, HERRAMIENTA, EQUIPO, DESPERDICIOS, ACARREOS, OPERACION Y MATERIALES DE CONSUMO. | M3 | 0.160000 | $900.28 | $144.04 |
| Suma de Auxiliar | $144.04 | ||||
| Contrato | |||||
| 104_SC | Subcontrato de 104 | ML | 1.000000 | $30.00 | $30.00 |
| Suma de Contrato | $30.00 | ||||
| Costo Directo | $382.09 |