| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 19.- | SOPORTE-PLATAFORMA Y MURETESDE CONCRETO F'C=250KG/CM2, REF. CON VARILLA DE 3/8" A CADA 20 CM., DE 20 CM. DE ESPESOR, PARA RAMPA NIVELADORA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-02 | ALAMBRE REC. | KG | 0.480000 | $8.82 | $4.23 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.000000 | $10.00 | $20.00 |
| CIMBRA-011 | CHAFLAN DE 1" | ML | 2.000000 | $4.00 | $8.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $8.27 | $28.12 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.400000 | $72.00 | $28.80 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $10.00 | $2.00 |
| ACERO-06 | ACERO DE NO. 3 | KG | 15.000000 | $6.52 | $97.80 |
| Suma de Material | $188.95 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.100000 | $1,109.21 | $110.92 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.400000 | $481.43 | $192.57 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.300000 | $481.43 | $144.43 |
| Suma de Mano de Obra | $447.92 | ||||
| Auxiliar | |||||
| CONCRETO H.O-01 | CONCRETO HECHO EN OBRA F'C = 250 KG/CM2. AGREGADO GRUESO MAXIMO DE 3/4" REVENIMIENTO 10 CM RESISTENCIA NORMAL, GRADO TIPO 'A' ESTRUCTURAL PARA FORMACION DE ZAPATAS INCLUYE: SUMINISTRO DE LOS MATERIALES, HERRAMIENTA, EQUIPO, DESPERDICIOS, ACARREOS, OPERACION Y MATERIALES DE CONSUMO. | M3 | 0.400000 | $900.28 | $360.11 |
| Suma de Auxiliar | $360.11 | ||||
| Costo Directo | $996.99 |