| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3,01.02.026.H.10 | CONCRETO HIDRAULICO COLADO EN SECO DE F'C=200 KG/CM2 ( 047-G.11.a.1 ) | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.020000 | $810.00 | $826.20 |
| CONCRETO PRE-02 | BOMBA PARA CONCRETO | M3** | 0.730000 | $198.00 | $144.54 |
| CIMBRA-04 | MADERA DE PINO | PT** | 1.250000 | $5.62 | $7.03 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 0.200000 | $77.26 | $15.45 |
| CIMBRA-02 | CLAVO | Kg.** | 4.500000 | $14.00 | $63.00 |
| Suma de Material | $1,056.22 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.150000 | $434.63 | $65.19 |
| Suma de Mano de Obra | $65.19 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO CIPSA KOHLER 8 HP BASE TIPO JAULA | HR | 0.137856 | $11.94 | $1.65 |
| Suma de Equipo | $1.65 | ||||
| Costo Directo | $1,123.06 |