| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ., | De f'c = 250 kg/cm² en dados de conexion. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO RESISTENTE A LOS SULFATOS Y ALCALISIS | M3 | 1.050000 | $1,125.00 | $1,181.25 |
| AGUA EN PIPA | AGUA PUESTA EN OBRA ACARREADA EN PIPA. | M3 | 0.060000 | $50.00 | $3.00 |
| PAVIMENTO-06 | MEMBRANA DE CURADO | LT | 0.150000 | $8.89 | $1.33 |
| CIMBRA-002 | MADERA DE PINO DE 4" X 4" X 4.87 | PT | 8.000000 | $7.50 | $60.00 |
| CONCRETO PRE-02 | SERVICIO DE BOMBEO | M3 | 1.050000 | $150.30 | $157.82 |
| CIMBRA-001-01 | CIMBRAPLAY | M2 | 0.100000 | $100.67 | $10.07 |
| CIMBRA-003 | CLAVO DE 2 1/2" A 4 1/2" | KG | 0.100000 | $13.04 | $1.30 |
| Suma de Material | $1,414.77 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.124362 | $569.07 | $70.77 |
| CUADRILLA CARO. ON | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.150000 | $759.16 | $113.87 |
| Suma de Mano de Obra | $184.64 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.137856 | $46.31 | $6.38 |
| Suma de Equipo | $6.38 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO RENTA POR DIA | DIA | 0.250000 | $59.11 | $14.78 |
| Suma de Auxiliar | $14.78 | ||||
| Costo Directo | $1,620.58 |