| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 4.1 | Sueldos y salarios trabajos de personal de campo | mes |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| COORD1 | COORDINADOR DE PROYECTO | jor | 60.000000 | $744.00 | $44,640.00 |
| ESPOHID1 | ESPECIALISTA EN OBRAS HIDR脕ULICAS | jor | 60.000000 | $697.50 | $41,850.00 |
| JEFPHID1 | JEFE DE PROYECTO HIDR脕ULICO | jor | 60.000000 | $651.00 | $39,060.00 |
| JEFPTOP1 | JEFE DE PROYECTO TOPOGR脕FICO | jor | 60.000000 | $651.00 | $39,060.00 |
| INGCHID | INGENIERO CIVIL HIDR脕ULICA | jor | 60.000000 | $496.00 | $29,760.00 |
| INGTOPO1 | INGENIERO TOPOGR脕FO | jor | 60.000000 | $496.00 | $29,760.00 |
| AYUDTOP1 | AYUDANTE DE TOPOGR脕FO | jor | 60.000000 | $310.00 | $18,600.00 |
| AYUDGRAL1 | AYUDANTE GENERAL | jor | 60.000000 | $248.00 | $14,880.00 |
| LANCH1 | Lanchero 1 | jor | 30.000000 | $263.50 | $7,905.00 |
| LANCH2 | Lanchero 2 | jor | 30.000000 | $263.50 | $7,905.00 |
| AYUDGRAL2 | Chal谩n 2 | jor | 60.000000 | $232.50 | $13,950.00 |
| AYUDGRAL3 | Chal谩n 3 | jor | 60.000000 | $232.50 | $13,950.00 |
| AYUDGRAL4 | Chal谩n 4 | jor | 60.000000 | $232.50 | $13,950.00 |
| Suma de Mano de Obra | $315,270.00 | ||||
| Costo Directo | $315,270.00 |