| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| II.14 | REPOSICION DE PISO DE CONCRETO F'C=200 KG/CM2, TAMAÑO MAXIMO DEL AGREGADO 3/4" DE 20 CM DE ESPESOR, ARMADO CON MALLA LACC 6/6-6/6 DOBLE PARRILLA, ACABADO PULIDO FINO INTEGRAL SOBRE CONCRETO FRESCO EN COLOR VERDE INTEGRAL. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 200 | CONCRETO PREMEZCLADO DE F'C=200 KG/CM2 | M3 | 0.210000 | $923.00 | $193.83 |
| MALLA 6/6 6-6 | MALLA ELECTROSOLDADA 6X6/ 6-6 | M2 | 2.200000 | $17.86 | $39.29 |
| COLOR IPOLIN VERDE | COLOR IPOLIN VERDE | KG | 2.000000 | $20.00 | $40.00 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.200000 | $80.10 | $16.02 |
| AGUA | AGUA ACARREO INTERNO | M3 | 0.042000 | $2.00 | $0.08 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.001000 | $857.58 | $0.86 |
| Suma de Material | $290.08 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.071429 | $1,719.42 | $122.82 |
| Suma de Mano de Obra | $122.82 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.007143 | $190.38 | $1.36 |
| LLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.044444 | $129.49 | $5.76 |
| Suma de Equipo | $7.11 | ||||
| Auxiliar | |||||
| JUNTA ASERRADA | JUNTA ASERRADA CON DISCO DE DIAMANATE Y SELLADO DE JUNTA CON SELLADOR Y CINTILLA DE RESPALDO O BACKER ROD 1/8" | ML | 0.500000 | $40.97 | $20.49 |
| Suma de Auxiliar | $20.49 | ||||
| Costo Directo | $440.50 |