| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TUXTEPEC-01 | RECIBIR TUBERIA DE LLEGADA DE 30" DE DIAMETRO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PREME-03 | CONCRETO PREMEZCLADO DE 250 KG/CM2 | M3 | 0.250000 | $1,185.28 | $296.32 |
| CONCRETO PREME-03 | CONCRETO PREMEZCLADO DE 250 KG/CM2 | M3 | 0.250000 | $1,185.28 | $296.32 |
| CONCRETO PREME-03 | CONCRETO PREMEZCLADO DE 250 KG/CM2 | M3 | 0.250000 | $1,185.28 | $296.32 |
| Suma de Material | $888.96 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.250000 | $689.83 | $172.46 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.250000 | $689.83 | $172.46 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.250000 | $689.83 | $172.46 |
| Suma de Mano de Obra | $517.37 | ||||
| Costo Directo | $1,406.33 |