| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4100 05 | APLANADO CON MORTERO CEMENTO-CAL-ARENA 1:1:4 DE 1.5 CM. DE ESPESOR. | M2. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-003 | AGUA | M3 | 0.040000 | $45.00 | $1.80 |
| Suma de Material | $1.80 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.125000 | $634.95 | $79.37 |
| Suma de Mano de Obra | $79.37 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO C-C-A 1:1:4 | Mortero cemento cal arena 1:1:4 | M3 | 0.015750 | $747.61 | $11.77 |
| Suma de Auxiliar | $11.77 | ||||
| Costo Directo | $92.94 |