| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6005 01 | DE 0.40 X 0.60 Y 0.50 MTS. DE PROFUNDIDAD. | PZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-006 | TABIQUE DE BARRO ROJO RECOCIDO | MILL | 0.188000 | $1,150.00 | $216.20 |
| REGISTRO-02 | MARCO Y CONTRAMARCO METALICO DE ANGULO 40X60 CM. | PZA | 1.000000 | $650.00 | $650.00 |
| Suma de Material | $866.20 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 1.500000 | $634.95 | $952.43 |
| Suma de Mano de Obra | $952.43 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.024000 | $895.94 | $21.50 |
| MORTERO 1:5 | mortero cemento arena 1:5 | m3 | 0.170000 | $753.62 | $128.12 |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.040000 | $803.95 | $32.16 |
| Suma de Auxiliar | $181.78 | ||||
| Costo Directo | $2,000.40 |