| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4100 06 | EMBOQUILLADO CON MORTERO CEMENTO-ARENA. | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CPOLÍN 3 1/2X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.300000 | $6.70 | $2.01 |
| Suma de Material | $2.01 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.050000 | $634.95 | $31.75 |
| Suma de Mano de Obra | $31.75 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO C-C-A 1:1:4 | Mortero cemento cal arena 1:1:4 | M3 | 0.003150 | $747.61 | $2.35 |
| SUMINISTRO DE AGUA | suministro de agua en pipa | m3 | 0.020000 | $47.00 | $0.94 |
| Suma de Auxiliar | $3.29 | ||||
| Costo Directo | $37.05 |