| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1005 01 | LIMPIEZA Y TRAZO EN EL AREA DE TRABAJO PARA DESPLANTE DE ESTRUCTURAS. | M2. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.025000 | $634.95 | $15.87 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.025000 | $634.95 | $15.87 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.025000 | $634.95 | $15.87 |
| Suma de Mano de Obra | $47.62 | ||||
| Concepto | |||||
| TRAZO | TRAZO | M2 | 1.000000 | $6.12 | $6.12 |
| TRAZO | TRAZO | M2 | 1.000000 | $6.12 | $6.12 |
| TRAZO | TRAZO | M2 | 1.000000 | $6.12 | $6.12 |
| Suma de Concepto | $18.36 | ||||
| Costo Directo | $65.98 |