| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 1600.B | SOPORTER脥A EN CISTERNA DE AGUA TRATADA, FABRICADA EN ACERO AL CARB脫N A-36 A BASE DE TUBER脥A, PERFILES ESTRUCTURALES Y PLACA, INCLUYE CORTES, BISELES, SOLDADURAS, TORNILLER脥A, EMPAQUES, ELMENTOS DE FIJACI脫N, ANCLAJE Y SOPORTE AS脥 COMO RECUBRIMIENTO EPOXICO A BASE DE LIMPIEZA A CHORRO DE ARENA A METAL BLANCO, DOS MANOS DE PRIMARIO EPOXICO DE ALQUITRAN DE HULLA (RP-5 "B") Y DOS MANOS DE ACABADO EPOXICO DE ALQUITRAN DE HULLA (RP-5 "B") CON ESPESOR M脥NIMO DE PELICULA SECA DE 4 MILESIMAS DE PULGADA POR CADA MANO. | kg |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MTSOL1 | SOLDADURA E-6010/7018 | KG. | 0.030000 | $32.60 | $0.98 |
| MTRP5 | RECUBRIMIENTO RP-5B | LT. | 0.010000 | $98.90 | $0.99 |
| MTAC36A | ACERO ESTRUCTURAL A36 | KG. | 0.650000 | $8.60 | $5.59 |
| MTPL36 | PLACA DE ACERO A-36 | KG. | 0.250000 | $9.10 | $2.28 |
| MTT6N | TUBO DE ACERO AL CARBON 6" DE DIAMETRO CEDULA 40 | ML | 0.010000 | $387.00 | $3.87 |
| Suma de Material | $13.70 | ||||
| Mano de Obra | |||||
| MOCU5. | CUADRILLA 5(PAILERIA) | JOR. | 0.002500 | $1,176.24 | $2.94 |
| Suma de Mano de Obra | $2.94 | ||||
| Equipo | |||||
| EQSOL1 | SOLDADORA MOTOR A COMB. INTERNA; 300A | HR | 0.008000 | $70.44 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Concepto | |||||
| BAREC1 | APLICACION RECUBRIMIENTOS ANTICORROSIVOS | HR. | 0.002500 | $100.97 | $0.25 |
| BASB1 | SANDBLASTEO | HR. | 0.003000 | $239.88 | $0.72 |
| Suma de Concepto | $0.97 | ||||
| Costo Directo | $18.18 |