| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 026 | CONSTRUCCION DE BANQUETA DE CONCRETO F'C=200 KG/CM2, ESPSOR DE 8 CMS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-04 | CONCRETO PREMEZCLADO DE F'C= 200 KG/CM2. | M3 | 0.084000 | $1,000.00 | $84.00 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.300000 | $7.50 | $9.75 |
| CLAVO | CLAVO | KG | 0.040000 | $13.08 | $0.52 |
| AGREGADO-003 | AGUA | M3 | 0.067000 | $45.00 | $3.02 |
| Suma de Material | $97.29 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.100000 | $634.95 | $63.50 |
| Suma de Mano de Obra | $63.50 | ||||
| Costo Directo | $160.78 |