| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 023 | CADENA DE DESPLANTE, INTERMEDIA Y CERRAMIENTO CON CONCRETO F'C= 150 KG/CM2, AGREGADO MAXIMO DE 3/4", CON SECCION DE 15x20 CM, CON 4 VAR. 3/8", E-2, A/C 20 CM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-03 | CONCRETO PREMEZCLADO DE F'C= 150 KG/CM. | m3** | 0.031500 | $850.00 | $26.78 |
| ACERO DIF. DIAM. | ACERO REF.VAR.DIAM. | kg | 2.540000 | $8.65 | $21.97 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.350000 | $7.50 | $10.13 |
| ALAMBRON | Acero de refuerzo núm. 2 (1/4" ) fyp = 2530 kg/ml | KG | 0.850000 | $10.00 | $8.50 |
| ALAMBRE REC. | ALAMBRE RECOCIDO | KG | 0.150000 | $13.50 | $2.03 |
| CLAVO | CLAVO | KG | 0.150000 | $13.08 | $1.96 |
| DIESEL | DIESEL | LT | 0.600000 | $5.60 | $3.36 |
| Suma de Material | $74.72 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.145000 | $634.95 | $92.07 |
| Suma de Mano de Obra | $92.07 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.040000 | $8.24 | $0.33 |
| Suma de Equipo | $0.33 | ||||
| Costo Directo | $167.12 |