| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1030 02.1 | DE F`c=150 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-003 | AGUA | M3 | 0.139860 | $45.00 | $6.29 |
| CONCRETO PRE-03 | CONCRETO PREMEZCLADO DE F'C= 150 KG/CM. | m3** | 1.030000 | $850.00 | $875.50 |
| FIBRA INTEGRAL | FIBRA INTEGRAL | M3 | 1.030000 | $80.00 | $82.40 |
| REVENIMIENTO | Revenimiento 14 +/- 3.5 cms | m3 | 0.250000 | $210.00 | $52.50 |
| SERVICIO DE BOMBEO | servicio de bombeo | m3 | 0.250000 | $130.00 | $32.50 |
| MEMBRANA DE CURADO | MEMBRANA DE CURADO | LT | 1.500000 | $9.50 | $14.25 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 16.250000 | $7.50 | $121.88 |
| CLAVO | CLAVO | KG | 0.500000 | $13.08 | $6.54 |
| Suma de Material | $1,191.86 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.100000 | $634.95 | $63.50 |
| Suma de Mano de Obra | $63.50 | ||||
| Costo Directo | $1,255.35 |