| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST. A-S | ESTRUCTURA DE TRANSICION AERO-SUBTERRANEA EN POSTE DE CONCRETO DE 12.50 M, PARA OPERACIÓN EN AMBIENTES TIPO COSTA, AISLADO A 34.5 KVA INDEPENDIENTEMENTE QUE OPERE A 23 KVA, INCLUYE CONOS DE ALIVIO, TUBERIA DE CANALIZACION, SISTEMA DE TIERRAS, CUCHILLAS DESCONECTADORAS, APARTARRAYOS, CRUCETAS Y ELEMENTOS DE SUJECIÓN DE ACUERDO A NORMAS CFE DE LA ZONA, INCLUYE MANO DE OBRA, EQUIPO, HERRAMIENTA, PRUEBAS Y PUESTA EN SERVICIO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CRUCETA PT200 | CRUCETA GALVANIZADA PT 200 NORMA CFE | PZA | 1.000000 | $224.00 | $224.00 |
| CCF 27 KV | CORTA CIRCUITO FUSIBLE 27 KV | PZA | 3.000000 | $642.60 | $1,927.80 |
| ESTRIBO | CONECTOR TIPO ESTRIBO PARA CABLE ACSR CAL.1/0 AWG | PZA | 3.000000 | $100.50 | $301.50 |
| APART | APARTARRAYO SINTETICO PARA 12 KV | PZA | 3.000000 | $534.80 | $1,604.40 |
| TOR3 | TORNILLO MAQUINA 5/8 X 8 " EXTRAGALVANIZADO | PZA | 4.000000 | $24.80 | $99.20 |
| PERICO | GRAPA PARA LINEA VIVA ( PERICO ) | PZA | 3.000000 | $75.00 | $225.00 |
| CU 4 | ALAMBRE DE COBRE DESNUDO 4 | KG | 10.000000 | $143.00 | $1,430.00 |
| H2 | TIRANTE PLANO H2 CHICO | PZA | 1.000000 | $40.10 | $40.10 |
| UL | ABRAZADERA UL | PZA | 1.000000 | $45.50 | $45.50 |
| ABRAZADERA 3BS | ABRAZADERA 3BS | PZA | 1.000000 | $35.70 | $35.70 |
| ESLABF5A | ESLABON FUSIBLE DE 5 AMP 15 KV | PZA | 3.000000 | $19.30 | $57.90 |
| SOP-1 | SOPORTE DE MADERA PARA CABLES DE POTENCIA | PZA | 1.000000 | $250.00 | $250.00 |
| TERMINAL 33 KV | TERMINAL TERMOCONTRACTIL EXTERIOR PARA 33 KV CAL 1/0 AWG MCA RAYCHEM | PZA | 3.000000 | $2,350.00 | $7,050.00 |
| BOTA | BOTA TEMOCONTRACTIL PARA TUBO DE 3" | PZA | 1.000000 | $633.70 | $633.70 |
| TUBO 44 | TUBO PAD COLOR NEGRO DE 4" TRAMO 6.10 MT | PZA | 1.500000 | $282.62 | $423.93 |
| FLEJE | FLEJE METALICO | ML | 5.500000 | $7.50 | $41.25 |
| VARILLA CPWLD | VARILLA COPERWELD PARA SISTEMA DE TIERRA DE 5/8" X 3.05 MTS | PZA | 1.000000 | $110.00 | $110.00 |
| CONECTOR VARILLA | CONECTOR PARA VARILLA 5/8" C/PROTOCOLO | PZA | 1.000000 | $50.50 | $50.50 |
| Suma de Material | $14,550.48 | ||||
| Mano de Obra | |||||
| AT | CUADRILLA ALTA TENSION 1 LINIERO + 2 AYUDANTE | jor | 1.000000 | $1,075.84 | $1,075.84 |
| Suma de Mano de Obra | $1,075.84 | ||||
| Equipo | |||||
| AEQHB5 | CAMION HIAB 5 TONS. | HR. | 3.000000 | $245.98 | $737.94 |
| Suma de Equipo | $737.94 | ||||
| Costo Directo | $16,364.26 |