| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| BLOCK LIG.15X20X40 | BLOCK DE CONCRETO LIGERO DE 15 X 20 X 40 CM. | MILL | 0.002500 | $8,000.00 | $20.00 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.050000 | $50.00 | $2.50 |
| Suma de Material | | | | $135.00 |
| Mano de Obra | | | | |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 0.150000 | $749.36 | $112.40 |
| Suma de Mano de Obra | | | | $674.42 |
| Auxiliar | | | | |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.010000 | $1,186.81 | $11.87 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| ANDAMIO METALICO6MTS | ANDAMIO DE 6 MTS DE ALTURA | DIA | 0.040000 | $111.22 | $4.45 |
| Suma de Auxiliar | | | | $97.90 |
| Costo Directo | | | | $907.33 |