| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3060 03 | CONSTRUCCION DE POZO DE VISITA DE 1.50 M DE DIAMETRO CON UNA ALTURA VARIABLE CON FONDO DE CONCRETO, APLANADO PULIDO INTERIOR MORTERO CEMENTO ARENA PROPORCION 1:3, INCLUYE EXCAVACION RELLENO, CONEXIÓN DE TUBOS Y MATERIALES NECESARIOS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CLAVO (VARIAS MED.) | CLAVO (VARIAS MED.) | Kg. | 5.000000 | $20.00 | $100.00 |
| CLAVO (VARIAS MED.) | CLAVO (VARIAS MED.) | Kg. | 5.000000 | $20.00 | $100.00 |
| VARILLA DIF. DIAM | VARILLA DIFERENTES DIAMETROS | TON | 0.025000 | $11,000.00 | $275.00 |
| VARILLA DIF. DIAM | VARILLA DIFERENTES DIAMETROS | TON | 0.025000 | $11,000.00 | $275.00 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | KG | 0.900000 | $15.00 | $13.50 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | KG | 0.900000 | $15.00 | $13.50 |
| TABIQUE ROJO RECOC. | TABIQUE DE BARRO RECOCIDO 5.5 X 12.5 X 25 CMS. | PZA | 2,965.000000 | $1.50 | $4,447.50 |
| TABIQUE ROJO RECOC. | TABIQUE DE BARRO RECOCIDO 5.5 X 12.5 X 25 CMS. | PZA | 2,965.000000 | $1.50 | $4,447.50 |
| ESCALON DE VARILLA | ESCALON DE VARILLA DE 1" Ø | PZA | 4.000000 | $25.00 | $100.00 |
| ESCALON DE VARILLA | ESCALON DE VARILLA DE 1" Ø | PZA | 4.000000 | $25.00 | $100.00 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.400000 | $50.00 | $20.00 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.400000 | $50.00 | $20.00 |
| Suma de Material | $9,912.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 3.500000 | $749.36 | $2,622.76 |
| CUADRILLA NO. 02 | CUADRILLA NO. 2 ( 1 ALBAÑIL + 1 PEON) | JOR | 3.500000 | $749.36 | $2,622.76 |
| CUADRILLA NO. 04 | CUADRILLA NO. 4 (1 FIERRERO + 1 AYUDANTE "B") | JOR | 0.500000 | $756.72 | $378.36 |
| CUADRILLA NO. 04 | CUADRILLA NO. 4 (1 FIERRERO + 1 AYUDANTE "B") | JOR | 0.500000 | $756.72 | $378.36 |
| Suma de Mano de Obra | $6,002.24 | ||||
| Auxiliar | |||||
| CONC.H/OF-C=250RN3/4 | CONCRETO HECHO EN OBRA F'C=250 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.642000 | $1,085.51 | $696.90 |
| CONC.H/OF-C=250RN3/4 | CONCRETO HECHO EN OBRA F'C=250 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.642000 | $1,085.51 | $696.90 |
| CADENA CONCRETO | CADENA DE CONCRETO f'c= 150 Kg/cm² DE 15 x 15 cm. ARMADA CON CUATRO VARILLAS DE 3/8" Y E. # 2 @ 20 cm. | ML | 3.140000 | $207.56 | $651.74 |
| CADENA CONCRETO | CADENA DE CONCRETO f'c= 150 Kg/cm² DE 15 x 15 cm. ARMADA CON CUATRO VARILLAS DE 3/8" Y E. # 2 @ 20 cm. | ML | 3.140000 | $207.56 | $651.74 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 1.482000 | $1,186.81 | $1,758.85 |
| MORTERO CEM-ARE 1:3 | MORTERO CEMENTO ARENA 1:3 | M3 | 1.482000 | $1,186.81 | $1,758.85 |
| Suma de Auxiliar | $6,214.98 | ||||
| Costo Directo | $22,129.22 |