| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01.02.027-H.03 | ACERO DE REFUERZO DE L.E. 4000 KG/CM2 | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO DE REF NO 8 | KG | 0.135700 | $5.80 | $0.79 | |
| ACERO DE REF NO 12 | KG | 0.699000 | $5.80 | $4.05 | |
| SOLDADURA DE UNION | BULBOS | KG} | 0.699000 | $0.70 | $0.49 |
| ACERO DE REF NO. 3 | KG | 0.195100 | $5.80 | $1.13 | |
| ALAMBRE RECOCIDO | KG | 0.030900 | $9.50 | $0.29 | |
| Suma de Material | $6.76 | ||||
| Mano de Obra | |||||
| OFICIAL FIERRERO | jor | 0.005000 | $416.89 | $2.08 | |
| AYUDANTE FIERRERO | jor | 0.005000 | $252.84 | $1.26 | |
| Suma de Mano de Obra | $3.35 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| DRAGA LINK BELT 108 | HR | 0.000100 | $895.51 | $0.09 | |
| Suma de Equipo | $0.09 | ||||
| Costo Directo | $10.19 |