| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01.02.026H-.10 | CONCRETO HIDRAULICO COLADO EN SECO F´C= 300 KG/CM2 (047 - G.11.a.1) | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DIESEL | LTO | 2.400000 | $4.90 | $11.76 | |
| CONC PREM F-C=300 | M3 | 1.030000 | $1,056.00 | $1,087.68 | |
| CONC PREM F-C=100 RN | M3 | 0.040000 | $738.00 | $29.52 | |
| MEMBRANA DE CURADO | lto | 0.800000 | $50.00 | $40.00 | |
| TRIPLAY | m2 | 0.488000 | $87.54 | $42.72 | |
| BARROTE DE PINO | PZA | 0.586000 | $38.00 | $22.27 | |
| CHAFLAN | ml | 5.332000 | $1.57 | $8.37 | |
| CLAVO PARA CONCRETO | kg | 0.200000 | $90.00 | $18.00 | |
| CLAVO DE 2" A 4" | KG | 0.800000 | $11.00 | $8.80 | |
| Suma de Material | $1,269.12 | ||||
| Mano de Obra | |||||
| OFICIAL ALBAÑIL | jor | 0.200000 | $416.89 | $83.38 | |
| AYUDANTE ALBAÑIL | jor | 0.200000 | $252.84 | $50.57 | |
| OFICIAL CARPINTERO | jor | 0.200000 | $416.89 | $83.38 | |
| AYUDANTE CARPINTERO | jor | 0.200000 | $252.84 | $50.57 | |
| Suma de Mano de Obra | $267.89 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| DRAGA LINK BELT 108 | HR | 0.050000 | $895.51 | $44.78 | |
| AMALI-017 | Vibrador de gasolina marca Dynapac modelo MVK8 cap. 12000 VPM, con chicote de 4.00 mts, por 38 mm ( 1 1/2"), con motor de gasolina de 4 H. P. | hora | 0.200000 | $53.82 | $10.76 |
| Suma de Equipo | $55.54 | ||||
| Costo Directo | $1,592.55 |