| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ELE-MED | SUMINISTRO E INSTALACION DE EQUIPO DE MEDICION INCLUYE: MEDIDOR DE CFE, MUFA, VARILLA, SUMINISTROS, COLOCACION, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION P.U.O.T. | PZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.G.P.G. 32MM. | ALIMENTACIÓN A TABLEROS DE DISTRIBUCIÓN CON TUBO CONDUIT PGG ROSCADO DE 32mm | ML* | 8.000000 | $40.13 | $321.04 |
| MUFA F.G. 2" | MUFA F.G. 2" | PZA | 1.000000 | $250.00 | $250.00 |
| CABLE THW-LS CAL 6 | CABLE THW-LS CALIBRE 6 MARCA CONDUMEX | Ml* | 20.000000 | $14.00 | $280.00 |
| CABLE THW-LS CAL 8 | CABLE THWLS. CAL. 8 | ML* | 6.000000 | $9.90 | $59.40 |
| VARILLA COPPERWEL | VARILLA COPPERWELD 5/8" X 3.05 M | PZA | 1.000000 | $165.00 | $165.00 |
| TUBO C.G.P.G. 19MM. | TUBO CONDUIT GALVANIZADO PARED GRUESA DE 19 MM DE DIAMETRO MARCA JUPITER O SIMILAR. | ML* | 3.000000 | $19.63 | $58.89 |
| CABLE CU DESN CAL 12 | CABLE CU DESNUDO CALIBRE 12 MARCA CONDUMEX | ML* | 25.000000 | $3.16 | $79.00 |
| BASE MED.13 TERMINAL | BASE MED.13 TERMINAL | PZA | 1.000000 | $3,300.00 | $3,300.00 |
| Suma de Material | $4,513.33 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 3.000000 | $707.65 | $2,122.95 |
| Suma de Mano de Obra | $2,122.95 | ||||
| Costo Directo | $6,636.28 |