| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| BGU-005A | GUARNICION SECCION 15X20X40 CM. DE CONCRETO PREMEZCLADO F'C=150 KG/CM2 INC. COMPACTACION, CIMBRA METALICA DE CONTACTO, VACIADO Y DESCIMBRADO | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-03 | CONCRETO PREMEZCLADO F'C=150KG/CM2 | M3 | 0.072100 | $700.00 | $50.47 |
| CIMBRA-04 | MADERA DE PINO | PT** | 0.050000 | $5.62 | $0.28 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 0.100000 | $77.26 | $7.73 |
| CIMBRA-02 | CLAVO | Kg.** | 0.060000 | $14.00 | $0.84 |
| Suma de Material | $59.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Pe贸n) | JOR | 0.090000 | $453.79 | $40.84 |
| Suma de Mano de Obra | $40.84 | ||||
| Costo Directo | $100.16 |