| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IV.08 | RENIVELACION DE POZO DE VISITA DE ACUERDO A NIVELES DE PROYECTO INCLUYE REPOSICION DE TAPA METALICA. | PZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABIQUE ROJO REC. | PZA. | 100.000000 | $0.90 | $90.00 | |
| CONCRETO DE 200. | CONCRETO DE PREMEZCLADO F'C=200 KG/CM2 CONCRETO PREMEZCLADO | M3 | 0.660000 | $684.40 | $451.70 |
| ACERO 05 | ACERODEL # 5 ( 5/8 ) | KG | 5.400000 | $5.50 | $29.70 |
| PINTURA-ESTRU-06 | GALVANIZADO POR INMERSION EN CALIENTE | KG | 5.400000 | $3.20 | $17.28 |
| MORTERO CEM-ARE. 1:4 | Mortero cemento arena 1:4 | M3 | 1.196000 | $566.77 | $677.86 |
| CONCRETO F-C=100 H/O | Concreto hecho en obra f'c = 100 kg/cm2agregado max. 3/4" R.N. | M3 | 0.164800 | $573.21 | $94.47 |
| BROCAL DE CONCR. | CON TAPA DE 60 CM. DE DIAM. | PZA | 1.000000 | $850.00 | $850.00 |
| Suma de Material | $2,211.01 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 3.000000 | $361.89 | $1,085.67 |
| CUADRILLA NO. 02 INS | (2 peones inst.,resanes, excavaciones, acarreos). | Jor. | 3.000000 | $304.98 | $914.94 |
| Suma de Mano de Obra | $2,000.61 | ||||
| Costo Directo | $4,211.62 |