| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IV.06 | SELLADO DE LA SUPERFICIE DE PAVIMENTO ASFALTICO APLICANDO EN FORMA DE BARRIDO CEMENTO PORTLAND EN PROPORCION DE 1 KG/M2 INCLUYE: MATERIALES, ACARREOS, FLETES, MANO DE OBRA, EQUIPO, HERRAMIENTA, MANIOBRAS, PERSONAL DE CONTROL, SEÑALAMIENTO DURANTE LOS TRABAJOS, PROTECCIONES, (P.U.O.T.) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-007 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,200.00 | $1.20 |
| ASALTO-004 | RIEGO DE ROMPIMIENTO MEDIO, INCLUYE DESPERDICIO. | LT | 1.000000 | $2.39 | $2.39 |
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.010000 | $40.00 | $0.40 |
| SELLO PARA CARPETA | SELLO PARA CARPETA ASFALTICA | M3 | 0.014200 | $550.00 | $7.81 |
| Suma de Material | $11.80 | ||||
| Equipo | |||||
| PETROLIZADORA | CAMION PETROLIZADORA | HR | 0.002500 | $272.23 | $0.68 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO | HR | 0.010000 | $245.83 | $2.46 |
| PIPA DE AGUA | PIPA DE AGUA | HR | 0.015000 | $161.25 | $2.42 |
| Suma de Equipo | $5.56 | ||||
| Costo Directo | $17.36 |