| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OBRA-EXT-04 | ANCLAJE DE CASTILLOS 15 X 15 CMS. CON CONCRETO F'C=150 KG/CM2 ARMADO CON 4 VARILLAS DEL # 3 (3/8") Y ESTRIBOS DEL N° 3 # (3/8") A CADA 15 CMS CIMBRA COMUN, INCUYE: CIMBRADO, DESCIMBRADO, COLOCACION, CONCRETO, MATERIALES Y MANO DE OBRA. | PZAS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO DEL # 3 | KG | 1.200000 | $6.00 | $7.20 |
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.009000 | $663.87 | $5.97 |
| ACERO-02 | ALAMBRE REC. | KG | 0.080000 | $8.90 | $0.71 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $6.00 | $6.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.160000 | $72.00 | $11.52 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.150000 | $11.00 | $1.65 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.600000 | $10.00 | $6.00 |
| Suma de Material | $39.06 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.100000 | $352.18 | $35.22 |
| Suma de Mano de Obra | $35.22 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR CONCRETO | HR | 0.300000 | $17.81 | $5.34 |
| Suma de Equipo | $5.34 | ||||
| Costo Directo | $79.62 |