| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OBRA-EXT-14 | FORJADO DE CANALON PERIMETRAL DE PILETA DE SECCION 25 X 15 CON CONCRETO F'C=150, KG/CM2 DE 20 X 20 CM PARA RECIBIR RECUBRIMIENTO CON PENDIENTE HACIA CARCAMO DE BOMBEO.DISEÑO SEGÚN PLANO INCLUYE: MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTO FUNCIONAMIENTO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.080000 | $663.87 | $53.11 |
| OEXTR-FESTER01 | FESTEGRAL | KG | 7.000000 | $9.80 | $68.60 |
| ACERO-01 | ACERO DEL # 3 | KG | 2.500000 | $6.00 | $15.00 |
| ACERO-02 | ALAMBRE REC. | KG | 0.075000 | $8.90 | $0.67 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 0.800000 | $6.00 | $4.80 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.200000 | $72.00 | $14.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $11.00 | $1.10 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 1.000000 | $10.00 | $10.00 |
| Suma de Material | $167.68 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 1.000000 | $352.18 | $352.18 |
| Suma de Mano de Obra | $352.18 | ||||
| Costo Directo | $519.86 |