| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OBRA-NEGR-07 | DALA DE CORONA DE CONCRETO F'C= 200 KG/CM2 TMA=3/4" DE 28 X 28 CMS, ARMADO CON 4 VARILLAS DEL # 3 (3/8") Y ESTRIBOS DEL #3 (3/8") CADA 20 CMS INCLUYE: CIMBRA COMUN, DESCIMBRA, COLADO, CURADO, CRUCES, E INTERSECCIONES DE LAS VARILLAS CON ELEMENTOS PERPENDICULARES, MATERIALES, HERRAMIENTAS, DESPEDICIS, MANO DEOBRA Y ACARREO DE MATERIALES AL SITIO DE SU UTILIZACION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO DEL # 3 | KG | 2.500000 | $6.00 | $15.00 |
| ACERO-022 | ALAMBRON | KG | 1.300000 | $8.00 | $10.40 |
| ACERO-02 | ALAMBRE REC. | KG | 0.080000 | $8.90 | $0.71 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.000000 | $6.00 | $6.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.180000 | $72.00 | $12.96 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.138100 | $11.00 | $1.52 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.600000 | $10.00 | $6.00 |
| Suma de Material | $52.59 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.166667 | $352.18 | $58.70 |
| Suma de Mano de Obra | $58.70 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR CONCRETO | HR | 1.000000 | $17.81 | $17.81 |
| Suma de Equipo | $17.81 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 | Concreto hecho en obra de f`c= 200 kg/cm2 | m3 | 0.080000 | $720.48 | $57.64 |
| Suma de Auxiliar | $57.64 | ||||
| Costo Directo | $186.74 |