| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-02 | CASTILLO DE CONCRETO SECCION = 28 X 20 CM, CONCRETO F´C=200 KG/CM2-3/4", CIMBRA 3 CARAS REFORZADO CON CUATRO VARILLAS R.N. DE 1/2" ESTRIBOS DE 1/4" A/C 25 CM. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| M-1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.912000 | $13.91 | $40.51 |
| M-0085-00 | VARILLA FY=4200 KG/CM2 Nº 4 (1/2") | KG | 4.183200 | $6.05 | $25.31 |
| M-0080-01 | ALAMBRON LISO DE 1/4" (NO. 2) | kg | 1.117400 | $6.88 | $7.69 |
| M-0082-05 | ALAMBRE RECOCIDO Nº 18 | KG | 0.200000 | $13.92 | $2.78 |
| M-0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.135000 | $6.77 | $0.91 |
| M-0950-05 | DIESEL | LT | 0.600000 | $4.94 | $2.96 |
| Suma de Material | $80.16 | ||||
| Mano de Obra | |||||
| CUA-041 | cuadrilla no 41 | jor | 0.200000 | $378.45 | $75.69 |
| Suma de Mano de Obra | $75.69 | ||||
| Herramienta | |||||
| FAHM | FACTOR DE HERRAMINETA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| FAES | FACTOR DE EQUIPO DE SEGURIDAD | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CON-200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2 RESISTENCIA NORMAL AGREGADO MAXIMO 3/4" | m3 | 0.058800 | $1,202.35 | $70.70 |
| ANDAMIO-02 | ANDAMIO DE CABLLETES | USO | 0.200000 | $14.46 | $2.89 |
| Suma de Auxiliar | $73.59 | ||||
| Costo Directo | $229.44 |