| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-03 | DALA DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION = 10 X 15 CM, CONCRETO F´C=200 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 10-4 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| M-1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $13.91 | $15.38 |
| M-0109-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 10-4 | M | 1.050000 | $11.08 | $11.63 |
| M-0082-05 | ALAMBRE RECOCIDO Nº 18 | KG | 0.200000 | $13.92 | $2.78 |
| M-0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $6.77 | $0.85 |
| M-0950-05 | DIESEL | LT | 0.400000 | $4.94 | $1.98 |
| Suma de Material | $32.62 | ||||
| Mano de Obra | |||||
| CUA-041 | cuadrilla no 41 | jor | 0.078400 | $378.45 | $29.67 |
| Suma de Mano de Obra | $29.67 | ||||
| Herramienta | |||||
| FAHM | FACTOR DE HERRAMINETA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| FAES | FACTOR DE EQUIPO DE SEGURIDAD | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CON-200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2 RESISTENCIA NORMAL AGREGADO MAXIMO 3/4" | m3 | 0.015700 | $1,202.35 | $18.88 |
| ANDAMIO-02 | ANDAMIO DE CABLLETES | USO | 0.078400 | $14.46 | $1.13 |
| Suma de Auxiliar | $20.01 | ||||
| Costo Directo | $82.31 |