| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LIM-01 | LIMPIEZA FINAL DE LA OBRA CON SOLUCION AGUA DETERGENTE EN POLVO Y ACIDO MURIATICO, INCLUYE PISOS, NUROS, VIDRIOS, ETC. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| M-1652-64 | DETERGENTE EN POLVO | KG | 0.150000 | $13.65 | $2.05 |
| M-2601-65 | ACIDO MURIATICO | LT | 0.100000 | $18.12 | $1.81 |
| Suma de Material | $3.86 | ||||
| Mano de Obra | |||||
| CUA-001 | cuadrilla no 01 | jor | 0.022200 | $162.75 | $3.61 |
| Suma de Mano de Obra | $3.61 | ||||
| Herramienta | |||||
| FAHM | FACTOR DE HERRAMINETA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| FAES | FACTOR DE EQUIPO DE SEGURIDAD | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ANDAMIO-02 | ANDAMIO DE CABLLETES | USO | 0.011100 | $14.46 | $0.16 |
| Suma de Auxiliar | $0.16 | ||||
| Costo Directo | $7.63 |