| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4070-06 | PLANTILLA DE CONCRETO ARMADA DE F'c=200 KG/CM2 DE 10 CM DE ESPESOR CON VARILLA # 3 @ 20 CM AMBOS SENTIDOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.010000 | $290.45 | $2.90 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.100000 | $233.90 | $23.39 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.100000 | $181.41 | $18.14 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.100000 | $169.01 | $16.90 |
| Suma de Mano de Obra | $61.34 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.100000 | $1,311.84 | $131.18 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 5.570000 | $22.84 | $127.22 |
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.400000 | $159.93 | $63.97 |
| Suma de Auxiliar | $322.37 | ||||
| Costo Directo | $383.71 |